8-31-2020 - West Bank River Parks trail will be closed for construction of the new low water dam. A detour for trail users will be HIGHLY marked and adds about 1.75 miles to the route. Construction expected to take 28 months.
UPDATE 1-20-2023 - Setbacks occurred when flows in the River breached the coffer dams requiring a shut down until flows went back to normal, followed by a lengthy process of restoring the coffer dams and mucking out the worksite. The current projection for the West Bank River Parks trail opening is now Summer 2023.