We’ve received many emails and calls about the Midland Valley Trail Renovation. First off, we would like to make clear that, while the Midland Valley Trail is linked to the River Parks’ trail, it is under the jurisdiction of the City of Tulsa, and not River Parks. That trail is maintained by Tulsa Parks, and they are coordinating the current renovation. We’re happy to see this renovation take place. Here is a list of things that we’ve learned from discussions with the City:
- The project is being done in two phases, 21st-26th, and 26th-Riverside. Each phase should take around 90 days. Only half of the trail will be blocked off at a time.
- Part of the parking lot at 31st and Riverside is being used as a construction staging area.
- The completion date for the project is slated for September.
- The trail will use the same lighting features as the River Parks trails.